Terminal Building 1 A & A Work at L6 & L7

To create additional retail space for T1 at CLK Airport for our client. This job covers the principal demolition methods and the associated precautionary measures for the removal of existing R.C. cantilevered slab along the various locations to facilitate the subsequent addition and alteration works.

1. The difficulties of this project are the working areas usually
located inside the public areas, such as lobby, main accesses
or shops. We need to maintain the normal operation for such
areas when carrying out our work.

 
2. Design and tailor-make the waterproofing facilites, Pre-test at
our workshopand then mobilize and install in airport.


 
 
3. Install the steel container under the demolition partition, then
using canvasto pass the slurry into the filter tank.







 
 
4. Set up the diamond wire saw machine to cut the RC element.


 
 
5. Lifting up and remove the cutted RC element by an A-frame



 
 
6. Indicate the overall coring positions, rectify or adjust where
necessary.

 
 
7. Set up the coring machine and core the holes for the further
bar fixing.
 
 
8. Cover the opened area with specially made steel pedestrian
plates.
 
Back
 

Tsim Sha Tsui MTR Station Demolition Work



Shatin Tai Wai New Town Stage 1 Phase 1 Bridge No.2 Demolition Work



Taikoo Place Linkage Demolition and Alteration Work


Copyright © Drillcut Ltd. All right reserved. Powered by Stoneast