Shatin Racecourse Alteration Work

Alteration work on 6/F, 7/F and 8/F of grandstand I in Shatin Racecourse – we widely used the hydraulic-powered crushers and hydraulic bursters in this project. With the help of the equipments, we can provide a noiseless, waterless and dust-free working environment. In the confined working space, we can still perform efficiently and flexibility in order to meet the tight deadline schedule.

Before

Fixing temporary ring hole platform below the demolish R.C. grandstand

Install soldier for temporary support

Core pre-drilled holes

Pre-drilled holes for inserted burster head

Use the crusher to demolish the parapet wall

Saw cut the R.C. beam

Break by electric breaker to retain the existing steel bars

Collect the debris to temporary deck

Remove the debris form the grandstand by mobile crane

Back
 

Tsim Sha Tsui MTR Station Demolition Work



Shatin Tai Wai New Town Stage 1 Phase 1 Bridge No.2 Demolition Work



Taikoo Place Linkage Demolition and Alteration Work


Copyright © Drillcut Ltd. All right reserved. Powered by Stoneast