Tseung Kwan O Depot Alteration and Addition Work

To form opening and proposed alteration and addition works of beams at Tseung Kwan O Depot. This job involves some basic demolition methods and another construction works (e.g. temporary lateral, support, grouting, fix steel reinforcement, formwork & pouring concrete.)

Welding temporary diagonal steel support on the existing structure

Form opening on existing structural wall

Set up certificated lifting eye on cut piece

Lifting up the cut piece and remove off site

Retained timber and steel support the in-situ R.C. beam

Modify the existing steel bar to lap the new structure

Fixing formwork for the new R.C. beam

Pouring concrete for the new R.C. beam

Fixing temporary single propps below demolition R.C. slab

Core holes to prevent overcut

Saw cut the R.C. slab to couple 300mm (w) concrete by blade saw machine

Back
 

Tsim Sha Tsui MTR Station Demolition Work



Shatin Tai Wai New Town Stage 1 Phase 1 Bridge No.2 Demolition Work



Taikoo Place Linkage Demolition and Alteration Work


Copyright © Drillcut Ltd. All right reserved. Powered by Stoneast